Skip to main content
Comptroller Main Webpage

The Clerk of the Board is responsible for keeping accurate minutes and maintaining Board records for each Board of County Commissioner (BCC) and Value Adjustment Board (VAB) meeting. In addition, every 4 years, the Clerk of the Board office provides staff support to the Charter Review Commission (CRC) appointed by the BCC. Please contact our office if you need an accessible version of documents on this page, and one will be provided.

Selection options are described below:

1. To search BCC records by meeting date and/or a specific term between September 23, 1869 and December 14, 2010, view the 'BCC Meetings' page.

2. To view BCC records by meeting date between January 4, 2011 through September 22, 2016, scroll down to locate the BCC meeting date.

3.
To search BCC records by a specific term between October 4, 2016 through Present, select the 'Search Records' tab.      

4.    To view VAB records by meeting date between June 20, 2013 through August 21, 2018, scroll down to locate the VAB meeting date. 

5.    To search CRC regular business meeting records by a specific term between February 25, 2019 through Present, select the 'Search Records' tab.

File #: 25-835    Version: 1 Name:
Type: Procurement Status: Passed
File created: 5/21/2025 In control: Administrative Services Department
On agenda: 6/17/2025 Final action: 6/17/2025
Title: Approval of Amendment No. 5, Contract Y19-817, Pump Station Master 3000 Pine Hills, with Black & Veatch, in the amount of $219,293.57, for a revised total contract amount of $1,744,231.18. ([Utilities Department Engineering Division] Procurement Division)

Interoffice Memorandum

 

DATE: May 21, 2025

 

TO: Mayor Jerry L. Demings and County Commissioners

 

FROM: Carrie Mathes, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division

 

CONTACT: Lindy A. Wolfe, P.E. LEED AP, Manager II, Utilities Engineering Division

 

PHONE: 407-254-9918

 

SUBJECT: Amendment No. 5, Contract Y19-817 Pump Station Master 3000 Pine Hills

 

ACTION REQUESTED:

title

Approval of Amendment No. 5, Contract Y19-817, Pump Station Master 3000 Pine Hills, with Black & Veatch, in the amount of $219,293.57, for a revised total contract amount of $1,744,231.18. ([Utilities Department Engineering Division] Procurement Division)

body


PROCUREMENT:

The project requires additional design services which were not included in the original scope, but are essential to fulfilling federal funding conditions, addressing County operational needs, and aligning with late-stage design directives by Orange County Utilities. The work ensures compliance, constructability, and long-term reliability of the infrastructure investment.

The additional design services are necessary to complete the construction documents phase prior to bidding.  The additional services are detailed as follows:

1.                     Replacement of Perimeter Fence with Blast-Proof Concrete Wall

As a condition of grant funding, the existing chain-link fence must be replaced with a blast-resistant concrete screen wall. The wall design impacted the layout of the yard piping.

2.                     Additional Revisions to Piping Design

The influent collection system changed due to new piping installations and removal of existing lines. Additional requests from the design review team during the construction documents phase required partial redesign.

3.                     Revisions to Process Mechanical Design

The Field Services Division requested the addition of a hatch to allow vac truck access for routine cleaning of the influent baffle wall. Additionally, they requested updates to the configuration of the level indicating transmitter and float installations to match their current operational standards.

4.                     Revisions to Structural Design

Structural design modifications to accommodate the revised process mechanical components.

5.                     Revisions to General Drawings and Specifications

FUNDING:

Funding is available in account number 4420-038-1559-0124-6310.

APPROVALS:

The Utilities Engineering Division concurs with this recommendation.

REMARKS:

The Board approved the selection of Black & Veatch on August 6, 2019. The contract was executed on August 1, 2020, in the not-to-exceed amount of $1,821,700, which encompasses engineering and support services related to preliminary engineering, design, and bidding services for the Pine Hills Pump Station 3000 and Pump Station 3849 Balcombe Road.

Prior contract amendments are as follows:

Contract executed with preliminary engineering, final design, and bidding services

                     Effective Date: 8/01/2020 Amount: $974,488.40

Amendment No. 1: preliminary and final design for Pine Hills Pump Station 3000

                     Effective Date: 4/09/2021 Amount: $57,078.35

                     Included additional surveying, groundwater sampling, and ecological services for environmental resource permit.

Amendment No. 2: additional engineering services for design revisions and construction administration

                     Effective Date: 04/27/2023 Amount: $314,331.56

                     Included reformatting the drawings so that Pump Station 3000 can be bid separately because it was awarded a grant from the Department of Economic Opportunity.  Additional work at Pump Station 3000 included changes in the upstream system that ties into this repump station and adding the Construction Phases Services that were not covered under any previous scopes or amendments. 

Amendment No. 3: additional design, bidding, and contract administration services

                     Effective Date: 12/05/2024 Amount: $47,142.31

                     Includes adding a subconsultant to design the perimeter fence.

Amendment No. 4: Additional Design, Bidding, and Contract Administration Services

                     Effective Date: 5/19/2025 $131,896.99

                     Additional engineering services prior to the bidding phase