Title: Approval of the award Invitation for Bids Y25-706-EB, Orange County Courthouse Lighting Upgrade, to the low responsive and responsible bidder, The Bridge Group Construction, Inc., in the total contract award amount of $4,823,844 inclusive of Additive No. 1 and Additive No. 2. ([Administrative Services Department Capital Projects Division] Procurement Division)
Attachments: 1. Y25-706 MWBE Evaluation (Base Bid plus Additive 1 & 2), 2. Y25-706-Spreadsheet (Base Bid plus Additive 1 & 2)

Interoffice Memorandum

 

DATE: February 7, 2025

 

TO: Mayor Jerry L. Demings and County Commissioners

 

FROM: Carrie Mathes, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division

 

CONTACT: Sara Flynn-Kramer, Manager II, Capital Projects Division

 

PHONE: 407-836-0048

 

SUBJECT: Award of Invitation for Bids Y25-706-EB, Orange County Courthouse                                                Lighting Upgrade

 

ACTION REQUESTED:

title

Approval of the award Invitation for Bids Y25-706-EB, Orange County Courthouse Lighting Upgrade, to the low responsive and responsible bidder, The Bridge Group Construction, Inc., in the total contract award amount of $4,823,844 inclusive of Additive No. 1 and Additive No. 2. ([Administrative Services Department Capital Projects Division] Procurement Division)

body


PROCUREMENT:

The project consists of replacing the existing 25-year-old lighting system with a more energy efficient and sustainable lighting system at the Orange County Courthouse buildings.  The base bid encompasses lighting upgrades in the basement and levels 1 through 25 of Building C tower at the Courthouse complex.  Additive No. 1 includes the lighting plan for the basement plus levels 1 through 5 of Building A and Additive No. 2 includes the lighting plan for the basement plus levels 1 through 5 of Building B. This project will increase efficiency and performance and will reduce energy costs.

FUNDING:

Funding is available in account number 1023-043-2088-3810.

APPROVALS:

The Capital Projects Division and Business Development Division concur with this recommendation.

REMARKS:

Three bids were received in response to this Invitation for Bids and were evaluated for responsiveness, responsibility and price reasonableness.  The bids submitted by CIC Construction Group USA, LLC. and Miller Electric Company were deemed non-responsive by the Procurement Division, based on the analysis provided by the Business Development Division, which identified the M/WBE participation goal was not achieved, and sufficient good faith effort documentation was not provided.

The bid tabulation is as follows:

 

BIDDERS                                                                                    BASE + ADDITIVE NO. 1 + ADDITIVE NO. 2

 

The Bridge Group Construction, Inc.                      $3,283,614    Base Bid

                                                                                                                                  $796,356   Additive No. 1

                                                                                                                                  $743,874   Additive No. 2

                                                                                                                               $4,823,844   Total Base Bid + Additives 1                                                                                                                                                                          and 2

 

CIC Construction Group USA, LLC.                     Non-Responsive

Miller Electric Company                                                               Non-Responsive