Interoffice Memorandum
DATE: July 7, 2026
TO: Mayor Jerry L. Demings and County Commissioners
FROM: Carrie Mathes, FNIGP, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division
CONTACT: Daniel Negron, P.E., CFM., Chief Engineer, Stormwater Management Division
PHONE: 407-836-7743
SUBJECT: Approval of Change Order No.1, Task Authorization No. 2, Contract Y24-911B Continuing Professional Engineering Stormwater Management Services
ACTION REQUESTED:
title
Approval of Change Order No.1, Task Authorization No. 2, Contract Y24-911B Continuing Professional Engineering Stormwater Management Services, with CDM Smith Inc, in the amount of $146,762.53, for a revised total amount of $499,940.15. ([Public Works Department Stormwater Management Division] Procurement Division)
body
PROCUREMENT:
Change Order No. 1 to this task authorization provides additional stormwater construction engineering inspection support. The amendment extends services by three months and includes two full-time inspectors (up to 1,040 labor hours) and additional project quality management coordination to support ongoing County construction activities. This supplemental support is necessary to maintain adequate inspection, documentation, and contractor oversight for ongoing County stormwater construction and MSBU maintenance activities. Existing staff cannot absorb the workload. Stormwater has only two MSBU Engineering Inspectors covering approximately 900 square miles, while the number of ponds requiring aquatic weed-control inspections has increased by 288, or 67%, and the number requiring mowing inspections has increased by 148, or 38%, since 2018. Last year, the two inspectors completed 12,424 inspections, excluding field verification, contractor coordination, resident inquiries, documentation, and reporting responsibilities.
FUNDING:
Funding is available in account number 1023-072-2753-3110.
APPROVALS:
The Stormwater Management Division concurs with this recommendation.
REMARKS:
On November 10, 2025, the Board approved the selection of CDM Smith Inc. to provide Continuing Engineering Stormwater Management Services for the Public Works Department.
Task Authorization No. 2 was executed on December 15, 2025, in the amount of $353,177.62 to facilitate periodic site inspections, identification of corrective actions, review of geotechnical test results, shop drawing reviews, and regulatory permit compliance inspections and support. These services are to be provided on an as requested and/or approved frequency basis.