Legislation Details

File #: 26-0761    Version: 1 Name:
Type: Recommendation Status: Consent Agenda
File created: 6/10/2026 In control: Administrative Services Department
On agenda: 6/30/2026 Final action:
Title: Approval of Change Order No 6, Contract Y24-714 Fire Station #32 Replacement - GRANT, with Mulligan Constructors Inc in the amount of $20,497.03, for a revised lump sum contract amount of $7,666,068.42. District 1. (Capital Projects Division)
Attachments: 1. 2026-06-30 Administrative Services Department Y24-714 Change Order 6.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 Interoffice Memorandum

 

DATE: June 9, 2026

 

TO: Mayor Jerry L. Demings and County Commissioners

 

THROUGH: N/A

 

FROM: Sara Flynn-Kramer, Manager, Capital Projects Division

 

CONTACT: Sara Flynn-Kramer

 

PHONE: 407-836-0048

 

DIVISION: Capital Projects

 

ACTION REQUESTED:

title

Approval of Change Order No 6, Contract Y24-714 Fire Station #32 Replacement - GRANT, with Mulligan Constructors Inc in the amount of $20,497.03, for a revised lump sum contract amount of $7,666,068.42.  District 1. (Capital Projects Division)

body


PROJECT:
Fire Station #32 Replacement - GRANT

 

PURPOSE: To provide funding for additional construction services to complete the capital improvements.

 

BUDGET: Accounting Line Number: 1046-034-0798-6210

 

JUSTIFICATION/DISCUSSION:

This cost is to reimburse the general contractor for extending Builder’s Risk and Pollution Liability Insurance coverage.  Construction could not start immediately after contract execution because of permitting issues resulting in an extension of the overall contract time.  This required the contractor to extend their insurance coverage beyond the advertised construction duration.

 

 

 

 

 

 

 

 

PREVIOUS ACTIONS TO THIS CONTRACT:

The Contract award was approved on February 6, 2024.

Original Contract dated March 5, 2024                                             Lump sum amount - $6,957,777.00

 

Change Order No. 1 dated December 10, 2024 Lump sum amount - $     42,819.34

Changes for substituted materials to deal with supply change issues

 

Change Order No. 2 dated April 2, 2025                        Lump sum amount - $   207,489.53

Changes per permit reviews

 

Change Order No. 3 July 28, 2025                                             Lump sum amount - $   172,617.66

Additional plan review comments and owner requests

 

Change Order No. 4 November 7, 2025                         Lump sum amount - $    84,797.08

Design conflicts and unforeseen conditions

 

Change Order No. 5 dated April 14, 2026                        Lump sum amount - $   180,070.78

Fire protection at gas range

 

Proposed Change Order No. 6                                                         Lump sum amount - $    20,497.03

Insurance extension

 

Proposed Final Contract Amount                                                          $ 7,666,068.42