Title: Approval of Change Order No. 3, Contract Y24-902B, Task Authorization No. 3, Seidel Road at Summerlake Groves Street Signal Improvement Project, with DRMP, Inc., in the amount of $9,643.44, for a revised total amount of $305,198.91. ([Public Works Department Traffic Engineering Division] Procurement Division)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Interoffice Memorandum

 

DATE: September 15, 2026

 

TO: Mayor Jerry L. Demings and County Commissioners

 

FROM: Carrie Mathes, FNIGP, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division

 

CONTACT: Humberto Castillero, Manager, Traffic Engineering Division

 

PHONE: 407-836-7891

 

SUBJECT: Approval of Change Order No. 3, Contract Y24-902B, Task Authorization No. 3, Seidel Road at Summerlake Groves Street Signal Improvement Project

 

ACTION REQUESTED:

title

Approval of Change Order No. 3, Contract Y24-902B, Task Authorization No. 3, Seidel Road at Summerlake Groves Street Signal Improvement Project, with DRMP, Inc., in the amount of $9,643.44, for a revised total amount of $305,198.91. ([Public Works Department Traffic Engineering Division] Procurement Division)

 

body


PROCUREMENT:

This change order authorizes additional professional services for the Seidel Road at Summerlake Groves Street Signal Improvement project. Following submittal of the Permit Exemption, the St. Johns River Water Management District (SJRWMD) determined that an Individual Permit with Minor Modification is required. This requirement was unforeseen and was not anticipated as part of the original project scope, as it exceeds permitting requirements previously applied to similar Orange County projects.

 

Additional services are required to address the Request for Additional Information issued by the SJRWMD and complete the permitting process.  This project is located in District 1.

 

FUNDING:

Funding is available on account number 1004-072-2720-3197.

APPROVALS:

The Traffic Engineering Division concurs with this recommendation.

REMARKS:

On May 21, 2024, the Board approved the selection of DRMP, Inc. to provide professional services through continuing contract Y24-902B that was executed September 5, 2024.  Subsequently, Task Authorization No. 3 was issued for the design and post-design of construction plans for traffic signalization and miscellaneous roadway improvements at the intersection of Seidel Road at Summerlake Groves Street and Seidel Road at Golden Harbor Lane in the total task authorization amount of $189,967.86. The Task Authorization was issued July 18, 2025.

Previous change orders to Task Authorization No. 3 are as follows:

Change Order No. 1: Added funds for additional services in the amount of $27,499.23, for a revised total amount of $217,467.09.

Change Order No. 2: Added funds for additional services in the amount of $78,088.38, for a revised total amount of $295,555.47.