Legislation Details

File #: 26-0935    Version: 1 Name:
Type: Recommendation Status: Consent Agenda
File created: 7/20/2026 In control: Administrative Services Department
On agenda: 8/4/2026 Final action:
Title: Approval of Change Order No. 4, Contract Y25-730 Orange County Sheriff's Criminal Division Renovation Project, with Core Engineering & Construction Inc in the amount of $20,747.50, for the replacement of CAT5 cabling with new CAT6 cabling, for a revised lump sum contract amount of $1,088,294.03. District 6. (Capital Projects Division)
Sponsors: Administrative Services-Real Estate Management
Attachments: 1. BCC Change Order 4
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Interoffice Memorandum

 

DATE: July 20, 2026

 

TO: Mayor Jerry L. Demings and County Commissioners

 

THROUGH: Carla Bell Johnson, Deputy County Administrator, County Administrator’s Office

 

FROM: Sara Flynn-Kramer, Manager, Capital Projects Division

 

CONTACT: Sara Flynn-Kramer

 

PHONE: 407-836-0043

 

DIVISION: Capital Projects

 

ACTION REQUESTED:

title

Approval of Change Order No. 4, Contract Y25-730 Orange County Sheriff’s Criminal Division Renovation Project, with Core Engineering & Construction Inc in the amount of $20,747.50, for the replacement of CAT5 cabling with new CAT6 cabling, for a revised lump sum contract amount of $1,088,294.03. District 6. (Capital Projects Division)

body


PROJECT:
Sheriff’s Criminal Investigation Division Renovation

 

PURPOSE: To provide funding to replace existing CAT5 cabling with new CAT6 cabling.

 

BUDGET: Accounting Line No.:1023-023-4435-3810

 

JUSTIFICATION/DISCUSSION:

This change order is necessary to provide data distribution to multiple locations per the approved drawings. CAT5 cabling has become obsolete and is being replaced with CAT6 cabling. CAT5 cabling was the ISS standard when design was completed.

 

 

PREVIOUS ACTIONS TO THIS CONTRACT:

The Contract award was approved on April 8, 2025.

Original Contract dated April 28, 2025                     
Lump sum amount - $975,833.99

The Contract award was approved on April 8, 2025.

Original Contract dated April 28, 2025                     
Lump sum amount - $975,833.99


Change Order No. 1
                                                                  
Lump sum amount - 5,405.02
Change order issued to replace designed 7’ tall doors with 8’ tall doors to match existing openings.

Change Order No. 2
                                                                 
Lump sum amount - $67,018.03
Change order issued for Additional LED light fixtures, additional millwork, and additional mechanical work.

Change Order No. 3
Lump sum amount - $19,289.49
Change order issued for replacement of existing fire sprinkler pendants for code compliance and additional breakroom millwork missed in design.

Proposed Change Order No. 4
                     
Lump sum amount - $20,747.50
Change order issued for replacement of existing CAT5 cabling with new CAT6 cabling.

Proposed Final Contract Amount - $1,088,294.03