Title: Approval of Change Order No 3, Contract Y23-821 Parks Lake Ellenor Community Park CP23055, with SK Consortium Inc in the amount of $20,817.61, for a revised lump sum contract amount of $458,063.39. District 6. (Capital Projects Division)
Attachments: 1. 2026-06-02-Administrative Services Department Consent Item-01
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Interoffice Memorandum

 

DATE: May 13, 2026

 

TO: Mayor Jerry L. Demings and County Commissioners

 

FROM: Sara Flynn-Kramer, Manager, Capital Projects Division

 

CONTACT: Sara Flynn-Kramer

 

PHONE: 407-836-0048

 

DIVISION: Capital Projects Division

 

ACTION REQUESTED:

title

Approval of Change Order No 3, Contract Y23-821 Parks Lake Ellenor Community Park CP23055, with SK Consortium Inc in the amount of $20,817.61, for a revised lump sum contract amount of $458,063.39. District 6. (Capital Projects Division)

body


PROJECT:
Parks Lake Ellenor Community Park

 

PURPOSE: To provide funding for additional design services to complete the capital improvements.

 

BUDGET: Accounting Line Number: 1265-062-2188-6310

 

JUSTIFICATION/DISCUSSION:

This additional design work is necessary to implement changes to the programming and the associated site layout, landscape, irrigation, electrical, and lighting work to accommodate the addition of the new small restroom and storage building which will be a bid additive.  This additional design work also includes the associated coordination and permit fees for the Florida Department of Environmental Protection and the South Florida Water Management District permits.

 

PREVIOUS ACTIONS TO THIS CONTRACT:

The Contract award was approved on September 12,2023.

Original Contract dated March 7, 2024                                                Lump sum amount - $   343,153.15

Change Order No. 1 dated December 10, 2024    Lump sum amount - $     42,261.81

Revision of 60% design documents resulting in the

addition and deletion of some of the park elements to

work within the budget by removing the site lighting

and relocate the fields

Change Order No. 2 dated March 13, 2026                         Lump sum amount - $    51,830.82 

Revision of 90% design documents to accommodate

scope changes

Proposed Change Order No. 3                                                          Lump sum amount - $    20,817.61

Site changes, irrigation and landscape design and permit

fee to accommodate the addition of the new small restroom

and storage building

Proposed Final Contract Amount                                                             $  458,063.39