Legislation Details

File #: 25-228    Version: 1 Name:
Type: Recommendation Status: Passed
File created: 1/23/2025 In control: Public Works Department
On agenda: 2/11/2025 Final action: 2/11/2025
Title: Approval and execution of Agreement between Orange County, Florida and Central Florida Expressway Authority regarding the westerly extension of New Independence Parkway. District 1. (Transportation Planning Division)
Attachments: 1. 25-228_2.11.2025_Agreement between Orange County FL and CFX regarding Westerly Extension of New Independence Pkwy, 2. 2025-02-11 Public Works Department Consent Item-02
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Interoffice Memorandum

 

DATE: January 23, 2025

 

TO: Mayor Jerry L. Demings and County Commissioners

 

THROUGH: N/A

 

FROM: Joseph C. Kunkel, P.E., Director, Public Works Department

 

CONTACT: Brian R. Sanders, Manager

 

PHONE: (407) 836-8022

 

DIVISION: Transportation Planning Division

 

ACTION REQUESTED:

title

Approval and execution of Agreement between Orange County, Florida and Central Florida Expressway Authority regarding the westerly extension of New Independence Parkway. District 1. (Transportation Planning Division)

body


PROJECT:
N/A

 

PURPOSE:
The Public Works Department is completing review of the final design, engineering, and permitting for the New Independence Parkway Extension westerly from Avalon Road (CR 545) to the Lake County line pursuant to the Town Center West (Silverleaf) Road Network Agreement (“Silverleaf Agreement”) approved by the Board on September 1, 2020. Lake County has their portion of Wellness Way (the name for New Independence Roadway in Lake County) from US 27 to the Orange County line currently under construction, and, together with Orange County’s project, will complete an important east-west connection in south Lake and west Orange Counties connecting US 27 to SR 429. 

While the roadway project is currently a delivery obligation of a private party, scheduling is largely dependent on available funding based on the pace of development activity within certain portions of the Horizon West Town Center. The design, engineering, and permitting and right of way phases are complete; however, the project will be funding constrained. Over the past several months, staff have worked with the developer to put together a funding package predicated on amendments to several public-private partnership agreements that would allow the County to assist in accelerating the New Independence Parkway Extension project.  

While a specific County contribution and funding agreement is still being finalized, Orange County and the Central Florida Expressway Authority (CFX) have negotiated the Agreement between Orange County, Florida and Central Florida Expressway Regarding the westerly extension of New Independence Parkway (“Agreement”) to provide for an additional contribution by CFX for the purpose of accelerating construction of New Independence Parkway which mutually benefits both agencies, serves a public purpose as a feeder road, and is consistent with CFX’s bond covenants. Upon approval of a road construction contract and confirmation that certain requirements under the Silverleaf Agreement have been satisfied, CFX has agreed to pay Orange County $2,500,000 as a grant contribution towards the New Independence Parkway Extension. 

The County Attorney’s Office, Risk Management Division and Transportation Planning Division have reviewed the Agreement as to form and found it acceptable.  

 

BUDGET: N/A