Comptroller Main Webpage

The Clerk of the Board is responsible for keeping accurate minutes and maintaining Board records for each Board of County Commissioner (BCC) and Value Adjustment Board (VAB) meeting. In addition, every 4 years, the Clerk of the Board office provides staff support to the Charter Review Commission (CRC) appointed by the BCC. Please contact our office if you need an accessible version of documents on this page, and one will be provided.

Selection options are described below:

1. To search BCC records by meeting date and/or a specific term between September 23, 1869 and December 14, 2010, view the 'BCC Meetings' page.

2. To view BCC records by meeting date between January 4, 2011 through September 22, 2016, scroll down to locate the BCC meeting date.

3.
To search BCC records by a specific term between October 4, 2016 through Present, select the 'Search Records' tab.      

4.    To view VAB records by meeting date between June 20, 2013 through August 21, 2018, scroll down to locate the VAB meeting date. 

5.    To search CRC regular business meeting records by a specific term between February 25, 2019 through Present, select the 'Search Records' tab.

File #: 24-1758    Version: 1 Name:
Type: Procurement Status: Passed
File created: 11/18/2024 In control: Administrative Services Department
On agenda: 12/17/2024 Final action: 12/17/2024
Title: Approval of Contract Y23-805, Final Engineering Design Services Pine Hills Road Trail Phase 2C (from Bonnie Brae Circle (Located 500' North of North Lane) to Clarcona Ocoee Road), with AVCON, Inc., in the total contract award amount of $740,548.99. ([Public Works Department Engineering Division] Procurement Division)

Interoffice Memorandum

 

DATE: November 18, 2024

 

TO: Mayor Jerry L. Demings and County Commissioners

 

FROM: Carrie Mathes, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division

 

CONTACT: Raymond Williams, Manager, Public Works Engineering Division

 

PHONE: 407-836-7909

 

SUBJECT: Approval of Contract Y23-805, Final Engineering Design Services Pine Hills Road Trail Phase 2C (from Bonnie Brae Circle (Located 500’ North of North Lane) to Clarcona Ocoee Road)

 

ACTION REQUESTED:

title

Approval of Contract Y23-805, Final Engineering Design Services Pine Hills Road Trail Phase 2C (from Bonnie Brae Circle (Located 500’ North of North Lane) to Clarcona Ocoee Road), with AVCON, Inc., in the total contract award amount of $740,548.99. ([Public Works Department Engineering Division] Procurement Division)

body


PROCUREMENT:

This contract will provide final engineering design of Pine Hills Road Trail Phase 2C from North Lane to Clarcona Ocoee Road for a distance of approximately one mile. This project is located in District 2.

FUNDING:

Funding is available through the Florida Department of Transportation (FDOT) Local Agency Program with supplemental funding by the County using the following account numbers:

                     7540-062-2129-6310 Grant Accounting Line

                     1265-062-2129-6310 Local Match Accounting Line

APPROVALS:

The Public Works Engineering Division concurs with this recommendation.

REMARKS:

On March 7, 2023, the Board approved the selection of AVCON, Inc. and authorized the Procurement Division to commence contract negotiations within an estimated budget of $600,000.  This amount was based on an in-house estimate completed in September 2019 using estimates of staffing hours and personnel rates from older contracts.  The project negotiations were delayed due in part to the reasons listed below.  

                     FDOT added a requirement for cultural resources assessment, which required the addition of sub-consultant Archaeological Consultants, Inc. (ACI).

o                     After ACI was added, FDOT mistakenly indicated ACI was not qualified to do this work.

o                     Further review from senior FDOT staff confirmed ACI is qualified when working under a prime consultant with appropriate FDOT qualifications.

                     After award, sub-consultant Gator Engineering & Aquifer Restoration, Inc., dba GEAR declined to participate and was required to be replaced by Drummond Carpenter, Inc.

                     Due to above delays, AVCON, Inc. and multiple sub-consultants had to process updated FDOT pre-qualification letters.

Due to the delays and inflation, the costs for the project were increased and an updated cost estimate was prepared in May 2023.  On June 2, 2023, FDOT provided concurrence to negotiate with AVCON, Inc. based on an updated engineering estimate of $913,619.81.  The final negotiated amount of $740,548.99 falls under the updated estimate and provides for appropriate staffing to ensure project success.