Legislation Details

File #: 26-0609    Version: 1 Name:
Type: Procurement Status: Discussion Item
File created: 5/7/2026 In control: Administrative Services Department
On agenda: 6/2/2026 Final action:
Title: Selection of one firm and three ranked alternates to provide Engineering Services for Lake Underhill Road Widening, Request for Proposals Y26-804-GO, from the following firms listed alphabetically: * AVCON, Inc. * Dewberry Engineers Inc. * NV5, Inc. * WBQ Design & Engineering, Inc. Further request Board authorization for the Procurement Division to negotiate and execute a contract within a not-to-exceed budget of $2,800,000. Further request Board authorization for the Procurement Division to formally terminate negotiations with the top ranked firm, if we are unable to come to a favorable negotiated agreement, and commence negotiations with the next ranked alternate, until a successful negotiation is reached. ([Public Works Department Engineering Division] Procurement Division)
Attachments: 1. Final Score Agenda, 2. BDD Y26-804 RFP Eval Memo Reviewed
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Interoffice Memorandum

 

DATE: May 7, 2026

 

TO: Mayor Jerry L. Demings and County Commissioners

 

FROM: Carrie Mathes, FNIGP, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division

 

CONTACT: Raymond Williams, P.E., Manager, Public Works Engineering Division

 

PHONE: 407-836-7909

 

SUBJECT: Selection of Firm, Request for Proposals, Y26-804-GO Engineering Services for Lake Underhill Road Widening

 

RECOMMENDATION:

title

Selection of one firm and three ranked alternates to provide Engineering Services for Lake Underhill Road Widening, Request for Proposals Y26-804-GO, from the following firms listed alphabetically:

 

                     AVCON, Inc.

                     Dewberry Engineers Inc.

                     NV5, Inc.

                     WBQ Design & Engineering, Inc.

 

Further request Board authorization for the Procurement Division to negotiate and execute a contract within a not-to-exceed budget of $2,800,000. 

 

Further request Board authorization for the Procurement Division to formally terminate negotiations with the top ranked firm, if we are unable to come to a favorable negotiated agreement, and commence negotiations with the next ranked alternate, until a successful negotiation is reached. ([Public Works Department Engineering Division] Procurement Division)

body


PROCUREMENT:

This contract will provide final engineering design for the Lake Underhill Road Widening, from 900’ east of Econlockhatchee Trail to 300’ west of Rouse Road. The Consultant shall provide professional services that will include, but not be limited to, preparation of construction plans, roadway design, drainage design, permitting, structural design, lighting, signalization design, landscaping, survey and geotechnical services, and coordination with utility companies, state and local agencies.  This project is located in Districts 3 and 4.

FUNDING:

Funding is available in account numbers 1312-072-5090-6311, 1023-072-5090-6311 and 1023-072-5115-6311.

DISCUSSION:

Six proposals were received in response to this Request for Proposals (RFP) and  evaluated in accordance with the criteria set forth in the RFP.  JE Estate was deemed non-responsive for failing to submit a valid proposal, none of the required forms were included in their submittal. DRMP, Inc. scored too low for Board consideration.

The Procurement Committee evaluated the proposals on April 29, 2026. Commissioner Mayra Uribe was assigned to the Procurement Committee.

The Procurement Committee’s consensus scores are attached.