Legislation Details

File #: 26-0722    Version: 1 Name:
Type: Procurement Status: Consent Agenda
File created: 5/29/2026 In control: Administrative Services Department
On agenda: 6/30/2026 Final action:
Title: Approval of Change Order No. 1, Purchase Order No. M121108, Waunatta Court Drainage Improvements, with RMS Constructors Group LLC, in the amount of $154,000, for a revised total amount of $211,000. ([Public Works Department Roads and Drainage Division] Procurement Division)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Interoffice Memorandum

 

DATE: May 29, 2026

 

TO: Mayor Jerry L. Demings and County Commissioners

 

FROM: Carrie Mathes, FNIGP, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division

 

CONTACT: Eduardo Avellaneda, M.S., P.E., Manager II, Roads and Drainage Division

 

PHONE: 407-836-7871

 

SUBJECT: Approval of Change Order No. 1, Purchase Order No. M121108, Waunatta Court Drainage Improvements

 

ACTION REQUESTED:

title

Approval of Change Order No. 1, Purchase Order No. M121108, Waunatta Court Drainage Improvements, with RMS Constructors Group LLC, in the amount of $154,000, for a revised total amount of $211,000. ([Public Works Department Roads and Drainage Division] Procurement Division)

body


PROCUREMENT:

This change order provides funding for additional lake treatment activities required as a result of design changes to the outfall end treatment. The original design included a headwall as the end treatment for the 36-inch diameter piped outfall discharging into the lake, to be constructed within an existing 14-foot wide drainage easement. However, the required width of a headwall for a 36-inch diameter pipe, in accordance with Florida Department of Transportation standards, is 15 feet, which exceeds the width of the drainage easement. This discrepancy was overlooked by the design engineer and was not identified until after the headwall had been installed in the field.

To comply with the easement constraints, the end treatment was revised from a headwall to a mitered end section. As a result, the originally anticipated seven days for dewatering, lake flocculation treatment, and erosion control measures associated with the headwall installation had to be extended by 28 additional days to allow for the coordination and implementation of the design changes.

FUNDING:

Funding is available in account number 1004-072-3010-6330.

APPROVALS:

The Roads and Drainage Division concurs with this recommendation.

REMARKS:

On April 23, 2026, Purchase Order M121108 was issued to RMS Constructors Group, LLC, in the amount of $57,000, for Waunatta Court Drainage Improvements - Off Contract Items associated with Delivery Order #358645.

Price reasonableness has been established, as the rates are the same as the rates approved of the original purchase order.