Skip to main content
Comptroller Main Webpage

The Clerk of the Board is responsible for keeping accurate minutes and maintaining Board records for each Board of County Commissioner (BCC) and Value Adjustment Board (VAB) meeting. In addition, every 4 years, the Clerk of the Board office provides staff support to the Charter Review Commission (CRC) appointed by the BCC. Please contact our office if you need an accessible version of documents on this page, and one will be provided.

Selection options are described below:

1. To search BCC records by meeting date and/or a specific term between September 23, 1869 and December 14, 2010, view the 'BCC Meetings' page.

2. To view BCC records by meeting date between January 4, 2011 through September 22, 2016, scroll down to locate the BCC meeting date.

3.
To search BCC records by a specific term between October 4, 2016 through Present, select the 'Search Records' tab.      

4.    To view VAB records by meeting date between June 20, 2013 through August 21, 2018, scroll down to locate the VAB meeting date. 

5.    To search CRC regular business meeting records by a specific term between February 25, 2019 through Present, select the 'Search Records' tab.

File #: 25-1408    Version: 1 Name:
Type: Recommendation Status: Consent Agenda
File created: 10/8/2025 In control: Public Works Department
On agenda: 10/28/2025 Final action:
Title: Approval of Change Order Number 3, Purchase Order M114783, 2024 Hurricane Season Pumping Support Orlo Vista Flood Mitigation Construction Project, with Thalle Construction Co., Inc. in the amount of $220,038.33, for a revised total amount of $1,574,863.97. District 6. (Stormwater Management Division)
Attachments: 1. 10.28.2025_25-1408_Thalle Change Order, 2. 10.28.2025_25-1408_BCC Orlo Vista Pumping CO3- Change Order Request
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Interoffice Memorandum

 

DATE: October 8, 2025

 

TO: Mayor Jerry L. Demings and County Commissioners

 

THROUGH: N/A

 

FROM: Joseph C. Kunkel, P. E., Director, Public Works Department

 

CONTACT: Michael J. Drozeck, P. E., CFM, Manager

 

PHONE: (407) 836-7945

 

DIVISION: Stormwater Management Division

 

ACTION REQUESTED:

title

Approval of Change Order Number 3, Purchase Order M114783, 2024 Hurricane Season Pumping Support Orlo Vista Flood Mitigation Construction Project, with Thalle Construction Co., Inc. in the amount of $220,038.33, for a revised total amount of $1,574,863.97. District 6. (Stormwater Management  Division)

body


PROJECT:
N/A

 

PURPOSE:
A change order in the amount of $220,038.33 for the Orio Vista Flood Mitigation Project is needed to cover the cost associated with the following:  additional month of bypass pumping (August), grounding (copper wire), concrete flume at 48” RCP, concrete flume at existing sluice gate, and North pond washout repair  The additional month of bypass pumping was required to manage pond levels with mobile pumps until the permanent pumps were connected to Duke Power, ensuring maximum storage and flood protection for the 2025 hurricane season. The construction of the two flumes is intended to prevent erosion at the connection between West Pond and Orlo Pond. The electrical inspector requested the installation of copper wire as the preferred option to meet Orange County standards. Finally, the washout repair on the north side of the North Pond is to provide a permanent solution to erosion caused by high water velocities entering the pond from State Road 408.   

PREVIOUS ACTIONS TO THIS CONTRACT: The original Emergency Purchase order M114783 was approved by the Board on May 21, 2024, for $610,948.76. 

Change Order No. 1 BCC Approved April 8, 2024                                       Amount: $216,561.00

Covered the costs associated with the following: a) Connecting two temporary pump discharge pipes to the pump station's spare 30-inch spare discharge port and b) Extending the emergency pumping from December 2024 through January 2025 to draw down and maintain the West Pond water level at elevation 62.00 ft.  

Change Order No. 2 BCC Approved May 6, 2025                                       Amount: $527, 315.88

Covered the costs associated with the following: a) Permanently installing the stormwater bypass system; b) Extending the emergency pumping through June 2025 to draw down and maintain the West Pond water level; and c) Extending the builder's risk insurance through the end of the project. 

Proposed Change Order No. 3                                                                                                      Amount: $220,038.33

Covers additional month of bypass pumping (August); grounding (copper wire); concrete flume at 48” RCP; concrete flume at existing sluice gate; and North Pond washout repair. 

Proposed Final Contract                                                                                                                                   Amount: $1,574,863.97

 

BUDGET: N/A