Legislation Details

File #: 26-0589    Version: 1 Name:
Type: Procurement Status: Consent Agenda
File created: 4/30/2026 In control: Administrative Services Department
On agenda: 6/2/2026 Final action:
Title: Approval of Change Order No. 3, Task Authorization No. 11, Contract Y22-905, Continuing Professional Consulting Services, Engineering and Inspection (CEI) Services, with CDM Smith, Inc., in the amount of $136,491.12, for a revised total amount of $499,846.32. ([Public Works Department Traffic Engineering Division] Procurement Division)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Interoffice Memorandum

 

DATE: April 30, 2026

 

TO: Mayor Jerry L. Demings and County Commissioners

 

FROM: Carrie Mathes, FNIGP, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division

 

CONTACT: Humberto Castillero, Manager, Traffic Engineering Division

 

PHONE: 407-836-7891

 

SUBJECT: Approval of Change Order No. 3, Task Authorization No. 11, Contract Y22-905, Continuing Professional Consulting Services, Engineering and Inspection (CEI) Services

 

ACTION REQUESTED:

title

Approval of Change Order No. 3, Task Authorization No. 11, Contract Y22-905, Continuing Professional Consulting Services, Engineering and Inspection (CEI) Services, with CDM Smith, Inc., in the amount of $136,491.12, for a revised total amount of $499,846.32. ([Public Works Department Traffic Engineering Division] Procurement Division)

body


PROCUREMENT:

This change order provides funding for an additional 1,040 man-hours required for staff augmentation services within the Traffic Engineering Division. The additional hours are necessary to support Construction Engineering and Inspection (CEI) services for the Y26-720-EB Seidel Road at Summerlake Park Boulevard Roundabout Improvement project throughout the full construction duration and project closeout phase. The construction timeline for Contract Y26-720 is estimated to take approximately 10 to 12 months, requiring CEI services to be provided throughout the entire construction process to ensure compliance with project specifications, safety standards, and contract requirements.

The additional CEI support will provide adequate staffing to perform daily construction inspections, coordinate with the contractor and project stakeholders, monitor project progress, maintain required project documentation, address field issues, and complete final project closeout activities.

FUNDING:

Funding is available in account number 1002-072-2711-3179.

APPROVALS:

The Traffic Engineering Division concurs with this recommendation.

REMARKS:

On August 9, 2022, the Board approved the selection of CDM Smith, Inc. to provide CEI Services.

Task Authorization No. 11 was executed on October 2, 2024, in the amount of $121,118.40.

Previous change orders for this Task Authorization are as follows:

Change Order No. 1: Extended the completion date by 275 days.

Change Order No. 2: Added staff augmentation services and funding in the amount of $242,236.80, for a revised total amount of $363,355.20, and extended the completion date by 375 days.