File #: 25-1056    Version: 1 Name:
Type: Recommendation Status: Passed
File created: 7/15/2025 In control: Administrative Services Department
On agenda: 8/5/2025 Final action: 8/5/2025
Title: Approval of Change Order No 3, Contract Y24-734 Hagood House Exterior and Interior Renovations, with Poli Construction Inc in the amount of $140,070.75, for a revised lump sum contract amount of $966,460.07. District 3. (Facilities Management Division)
Attachments: 1. 2025-08-05-Administrative Services Department Consent Item-01, 2. 2025-08-05 Administrative Services Department Consent Item-01 - Executed

Interoffice Memorandum

 

DATE: July 15, 2025

 

TO: Mayor Jerry L. Demings and County Commissioners

 

THROUGH: Anne Kulikowski, Director, Administrative Services Department

 

FROM: Rich Steiger, Manager, Facilities Management Division

 

CONTACT: Rich Steiger

 

PHONE: 407-836-7473

 

DIVISION: Facilities Management

 

ACTION REQUESTED:

title

Approval of Change Order No 3, Contract Y24-734 Hagood House Exterior and Interior Renovations, with Poli Construction Inc in the amount of $140,070.75, for a revised lump sum contract amount of $966,460.07.  District 3. (Facilities Management Division)

body


PROJECT:
Hagood House Exterior and Interior Renovations

 

PURPOSE: To provide funding for additional construction services to complete the capital improvements.

 

BUDGET: Accounting Line Number: 1023-043-0263-3810

 

JUSTIFICATION/DISCUSSION:

An assessment of the Hagood House located on the Great Oaks Village campus was performed in 2020 to review and provide recommendations for the replacement of the exterior wood siding and damaged interior floors due to termite activity. The assessment did not review the construction of the front entrance because the structural issues were not an issue at the time of the assessment.

 

Upon removing the old wood siding on the front entrance area, it was found that the front entrance over-hang was lacking the required structural support and connections to meet code. This presented a safety concern that required the design team to provide construction plans to provide structural connections and support to bring the front entrance up to code. This work will ensure the safety of the building occupants who use the front entrance and bring the entrance up to code. 

 

This change order includes the renovation of the front entrance, consisting of the removal of existing column wraps, demolition of the porch floor, and installation of new column footings, HSS steel columns and beams, a steel deck, and new FRP wraps. Work also includes concrete pouring, installation of new quarry tiles, a new railing system, and paint touch-ups to surrounding areas.

 

PREVIOUS ACTIONS TO THIS CONTRACT:

Original Contract dated August 30, 2024                     Lump sum amount - $   747,743.00 

 

Change Order No. 1 dated April 18, 2025                     Lump sum amount - $    46,389.31

Repairs needed for rotting fascia and 2nd FL carpet removed

and replaced with the same LVT being used on the first floor.

 

Change Order No. 2 dated June 3, 2025                     Lump sum amount - $     32,257.01

Additional painting needed to ceilings on first floor, install

walk-off areas and LVT flooring

 

Proposed Change Order No. 3                                                      Lump sum amount - $   140,070.75

Correct structural issues to the front porch that were

discovered upon the removal of the siding.

 

Proposed Final Contract Amount                                                       $  966,460.07