Skip to main content
Comptroller Main Webpage

The Clerk of the Board is responsible for keeping accurate minutes and maintaining Board records for each Board of County Commissioner (BCC) and Value Adjustment Board (VAB) meeting. In addition, every 4 years, the Clerk of the Board office provides staff support to the Charter Review Commission (CRC) appointed by the BCC. Please contact our office if you need an accessible version of documents on this page, and one will be provided.

Selection options are described below:

1. To search BCC records by meeting date and/or a specific term between September 23, 1869 and December 14, 2010, view the 'BCC Meetings' page.

2. To view BCC records by meeting date between January 4, 2011 through September 22, 2016, scroll down to locate the BCC meeting date.

3.
To search BCC records by a specific term between October 4, 2016 through Present, select the 'Search Records' tab.      

4.    To view VAB records by meeting date between June 20, 2013 through August 21, 2018, scroll down to locate the VAB meeting date. 

5.    To search CRC regular business meeting records by a specific term between February 25, 2019 through Present, select the 'Search Records' tab.

File #: 26-0355    Version: 1 Name:
Type: Recommendation Status: Consent Agenda
File created: 3/4/2026 In control: Administrative Services Department
On agenda: 3/24/2026 Final action:
Title: Approval of Change Order No 5, Contract Y24-773 Tangelo Park Community Center - GRANT CP21048, with Collage Companies in the amount of $1,806.21, for a revised lump sum contract amount of $7,746,668.51. District 6. (Capital Projects Division)
Attachments: 1. 2026-03-24-Administrative Services Department Consent Item-01
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Interoffice Memorandum

 

DATE: March 4, 2026

 

TO: Mayor Jerry L. Demings and County Commissioners

 

THROUGH: Anne Kulikowski, Director, Administrative Services Department

 

FROM: Sara Flynn-Kramer, Manager, Capital Projects Division

 

CONTACT: Sara Flynn-Kramer

 

PHONE: 407-836-0048

 

DIVISION: Capital Projects

 

ACTION REQUESTED:

title

Approval of Change Order No 5, Contract Y24-773 Tangelo Park Community Center - GRANT CP21048, with Collage Companies in the amount of $1,806.21, for a revised lump sum contract amount of $7,746,668.51.  District 6. (Capital Projects Division)

body


PROJECT:
Tangelo Park Community Center - GRANT

 

PURPOSE: To provide funding for additional construction services to complete the capital improvements.

 

BUDGET: Accounting Line Number: 1246-062-2568-6210

 

JUSTIFICATION/DISCUSSION:

The cost is to provide and install one structural tube steel column to support the entrance storefront system. This column was not shown on the structural plans, but it was discovered during the review of the shop drawings for the storefront, so no re-work was required to add this missing support column.

 

PREVIOUS ACTIONS TO THIS CONTRACT:

The Contract award was approved on August 27, 2024.

Original Contract dated September 3, 2024                          Lump sum amount - $7,041,570.00

Change Order No. 1 dated May 23, 2025                          Lump sum amount - $     51,547.76

Permit fees, concrete demo, and ballistic glass

Change Order No. 2 dated September 17, 2025  Lump sum amount - $   169,929.77 

De-mucking and conformed set permit revision work

Change Order No. 3 dated November 7, 2025     Lump sum amount - $   381,345.16 

Dewatering and de-mucking

Change Order No. 4 dated December 26, 2025   Lump sum amount - $   100,469.61 

Extended General Conditions for permitting & soil delays

Proposed Change Order No. 5                                                          Lump sum amount - $       1,806.21

Add on structural tube steel column at the storefront

Proposed Final Contract Amount                                                            $7,746,668.51