Comptroller Main Webpage

The Clerk of the Board is responsible for keeping accurate minutes and maintaining Board records for each Board of County Commissioner (BCC) and Value Adjustment Board (VAB) meeting. In addition, every 4 years, the Clerk of the Board office provides staff support to the Charter Review Commission (CRC) appointed by the BCC. Please contact our office if you need an accessible version of documents on this page, and one will be provided.

Selection options are described below:

1. To search BCC records by meeting date and/or a specific term between September 23, 1869 and December 14, 2010, view the 'BCC Meetings' page.

2. To view BCC records by meeting date between January 4, 2011 through September 22, 2016, scroll down to locate the BCC meeting date.

3.
To search BCC records by a specific term between October 4, 2016 through Present, select the 'Search Records' tab.      

4.    To view VAB records by meeting date between June 20, 2013 through August 21, 2018, scroll down to locate the VAB meeting date. 

5.    To search CRC regular business meeting records by a specific term between February 25, 2019 through Present, select the 'Search Records' tab.

File #: 24-1280    Version: 1 Name:
Type: Procurement Status: Passed
File created: 8/19/2024 In control: Administrative Services Department
On agenda: 9/10/2024 Final action: 9/10/2024
Title: Approval of Amendment No. 4, Task Authorization No. 1, Contract Y20-824, Ficquette Road Utility Improvements, with CPH, Inc., in the amount of $184,116.90, for a revised total award amount of $1,111,896.93. ([Utilities Department Engineering Division] Procurement Division)

Interoffice Memorandum

 

DATE: August 19, 2024

 

TO: Mayor Jerry L. Demings and County Commissioners

 

FROM: Carrie Mathes, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division

 

CONTACT: Lindy A. Wolfe, P.E. LEED AP, Manager II, Utilities Engineering Division

 

PHONE: 407-254-9918

 

SUBJECT:  Amendment No. 4, Task Authorization No. 1, Contract Y20-824, Ficquette Road Utility Improvements

 

ACTION REQUESTED:

title

Approval of Amendment No. 4, Task Authorization No. 1, Contract Y20-824, Ficquette Road Utility Improvements, with CPH, Inc., in the amount of $184,116.90, for a revised total award amount of $1,111,896.93. ([Utilities Department Engineering Division] Procurement Division)

body


PROCUREMENT:

Due to internal Orange County coordination, the current utilities design will need to be significantly altered to meet the changes requested by the Public Works Department to modify the design to minimize the amount of pipes to be under the pavement requiring a redesign of the plans. The change order scope includes additional engineering services to redesign a portion of the original design, provide additional design submittals, prepare a maintenance of traffic plan for the utility work, and add additional construction administration services for additional coordination during construction due to the changes. This project is located in District 1.

FUNDING:

Funding is available in account numbers 4420-038-1411-0072-6345, 4420-038-1504-0068-6345 and 4420-038-1482-0059-6345.

APPROVALS:

The Utilities Engineering Division concurs with this recommendation.

REMARKS:

On July 28, 2020, the Board authorized the selection of CPH, Inc. for Request for Proposals Y20-824 and authorized negotiation and execution of a contract by the Procurement Division provided that the contract does not exceed the budget amount of $1,700,000 for all phases of negotiation. This change order will exceed the budget amount previously approved by the Board.

Below is the purchase order history:

Purchase Order No. C20824: Issued Date: 6/4/2021 Amount: $350,000 (partial encumbrance)

Amendment No. 1: Issued Date: 1/29/2021 Amount: $0.00

To correct typo of total award amount to $902,204.78.

Amendment No. 2: Issued Date: 6/1/2022 Revised Amount: $624,924.45

Issued to encumber $274,924.45.

Amendment No. 3: Issued Date: 1/4/2023 Revised Amount: $650,499.70

Additional design services in the amount of $25,575.25. The additional design services were for evaluating and re-designing the current plans to relocate any proposed mains within the roadway to outside of pavement, prepare a maintenance of traffic plan and additional milestones submittals.