Title: Approval of Change Order No. 4, Task Authorization No. 1, Contract Y20-905B, Additional Engineering Services for East Water Reclamation Facility (EWRF) Motor Control Center Replacement, with Black & Veatch, in the total amount of $163,538.66, for a revised total award amount of $662,799.13. ([Utilities Department Engineering Division] Procurement Division)
Attachments: 1. 2024-06-18 Administrative Services Department Consent Item-09

title

Approval of Change Order No. 4, Task Authorization No. 1, Contract Y20-905B, Additional Engineering Services for East Water Reclamation Facility (EWRF) Motor Control Center Replacement, with Black & Veatch, in the total amount of $163,538.66, for a revised total award amount of $662,799.13. ([Utilities Department Engineering Division] Procurement Division)