File #: 26-1026    Version: 1 Name:
Type: Procurement Status: Consent Agenda
File created: 8/10/2026 In control: Administrative Services Department
On agenda: 9/15/2026 Final action:
Title: Approval of Change Order No. 8, Task Authorization No. 3, Contract Y23-904C, Continuing Engineering Services for the Utilities Department for the Wekiwa Retrofit Projects Phase 6A (Majestic Oaks) and Phase 6B (Sweetwater Country Club Place), with CPH, LLC in the amount of $258,846.76, for a revised total amount of $388,115.07. ([Utilities Department Engineering Division] Procurement Division)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Interoffice Memorandum

DATE: September 15, 2026

TO: Mayor Jerry L. Demings and County Commissioners

FROM: Carrie Mathes, FNIGP, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division

CONTACT: Lindy A. Wolfe, P.E. LEED AP, Manager II, Utilities Engineering Division

PHONE: 407-254-9918

SUBJECT: Approval of Change Order No. 8, Task Authorization No. 3, Contract Y23-904C, Continuing Engineering Services for the Utilities Department for the Wekiwa Retrofit Projects Phase 6A (Majestic Oaks) and Phase 6B (Sweetwater Country Club Place)

ACTION REQUESTED:
title
Approval of Change Order No. 8, Task Authorization No. 3, Contract Y23-904C, Continuing Engineering Services for the Utilities Department for the Wekiwa Retrofit Projects Phase 6A (Majestic Oaks) and Phase 6B (Sweetwater Country Club Place), with CPH, LLC in the amount of $258,846.76, for a revised total amount of $388,115.07. ([Utilities Department Engineering Division] Procurement Division)
body

PROCUREMENT:
The Wekiwa Retrofit Projects, which include Phase 6A – Majestic Oaks (59 parcels) and Phase 6B – Sweetwater Country Club Place (24 parcels), are funded by the Florida Department of Environmental Protection (FDEP) Grant – Agreement No. WG015 and will convert a total of 83 residential parcels from septic to sewer. To ensure applicable grant deadlines were met and the project remained on schedule, the original task authorization was negotiated to initially include surveying services for 24 residential lots, allowing survey activities to commence while the design was being finalized. The design services were subsequently incorporated into the task authorization through Change Order No. 1.
To comply with the FDEP grant timelines, the engineering scope under Task Authorization No. 3 was intentionally phased, initially limiting the purchase order to survey and design services for Phase 6B. Now that both Phase 6A (Majestic Oaks) and Phase 6B (Sweetwater Country Club Place) are advancing together i...