Interoffice Memorandum
DATE: October 22, 2024
TO: Mayor Jerry L. Demings and County Commissioners
FROM: Carrie Mathes, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division
CONTACT: Lindy A. Wolfe, P.E. LEED AP, Manager II, Utilities Engineering Division
PHONE: 407-254-9918
SUBJECT: Amendment No. 3, Contract Y17-811 Southwest Service Area Potable Water Storage and Repump Facility (SWSA SRF)
ACTION REQUESTED:
title
Approval of Amendment No. 3, Contract Y17-811, Southwest Service Area Potable Water Storage and Repump Facility (SWSA SRF), with Hazen and Sawyer, P.C., in the amount of $375,507.18, for a revised contract amount of $1,524,781.70. ([Utilities Department Engineering Division] Procurement Division)
body
PROCUREMENT:
This amendment adds funds to support additional construction administration services due to unforeseen conditions caused by 25 months of construction delays, mainly from material and resource shortages, delivery issues, wet weather, private development construction conflicts, and failed inspections later requiring consultant reinspection. Extra efforts are needed for responding to addendum items, reviewing supplementary shop drawings, and managing these delays. This amendment covers additional construction administration engineering services beyond the original scope of the SWSA SRF project to account for the extended construction duration. The amendment also added 720 days to the project timeframe.
FUNDING:
Funding is available in account number 4420-038-1506-0030-6340.
APPROVALS:
The Utilities Engineering Division concurs with this recommendation.
REMARKS:
This amendment provides for additional engineering services required by the County for the SWSA SRF. The additional services are required for Hazen and Sawyer, P.C. to continue the construction administration services for the extended project construction phase. The construction administration services include:
* Additional meetings
* Additional site visits and inspection...