Title: Approval of Change Order Number 1, Purchase Order M114783, Emergency Connection of Temporary Pumps to the Existing Pump Station and Additional Pumping, with Thalle Construction Co., Inc. in the amount of $216,561, for a revised total amount of $827,509.76. District 6. (Stormwater Management Division)
Attachments: 1. 25-547_4.8.2025_2024 Hurricane Season Pumping Support Orlo Vista Flood Mitigation

Interoffice Memorandum

 

DATE: March 20, 2025

 

TO: Mayor Jerry L. Demings and County Commissioners

 

THROUGH: N/A

 

FROM: Joseph C. Kunkel, P. E., Director, Public Works Department

 

CONTACT: Michael J. Drozeck, P. E., CFM, Manager

 

PHONE: (407) 836-7945

 

DIVISION: Stormwater Management Division

 

ACTION REQUESTED:

title

Approval of Change Order Number 1, Purchase Order M114783, Emergency Connection of Temporary Pumps to the Existing Pump Station and Additional Pumping, with Thalle Construction Co., Inc. in the amount of $216,561, for a revised total amount of $827,509.76. District 6. (Stormwater Management Division)

body


PROJECT:
N/A

 

PURPOSE:
A change order in the amount of $216,561 for the Orlo Vista Flood Mitigation Project is needed to cover the cost associated with the following: a) connecting two temporary pump discharge pipes to the pump station’s spare 30-inch spare discharge port and b) extending the emergency pumping from December 2024 through January 2025 to drawdown and maintain the West Pond water level at elevation 62 ft. The temporary pumps supplement the existing pump station's capacity and act as a backup to the pump station in case of failure during large storm events. This is critical to maximize available storage/flood protection in advance of the 2025 hurricane season.  

The original Emergency Purchase order M114783 was approved by the Board on May 21, 2024, for the emergency pumping during the 2024 Hurricane Season (June through November). 

 