Legislation Details

File #: 26-1211    Version: 1 Name:
Type: Recommendation Status: Consent Agenda
File created: 9/23/2026 In control: Administrative Services Department
On agenda: 10/13/2026 Final action:
Title: Approval of Change Order No 4, Contract Y25-704 Multicultural Center for Design & Innovation and Senior Center Construction, with Mulligan Constructors in the amount of $2,326,135.47, for a revised lump sum contract amount of $16,808,250.38. District 6. (Capital Projects Division)
Attachments: 1. C25704 Mulligan Constructors Change Order
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Interoffice Memorandum

 

DATE: September 21, 2026

 

TO: Mayor Jerry L. Demings and County Commissioners

 

THROUGH: N/A

 

FROM: Sara Flynn-Kramer, Manager, Capital Projects Division

 

CONTACT: Sara Flynn-Kramer

 

PHONE: 407-836-0048

 

DIVISION: Capital Projects

 

ACTION REQUESTED:

title

Approval of Change Order No 4, Contract Y25-704 Multicultural Center for Design & Innovation and Senior Center Construction, with Mulligan Constructors in the amount of $2,326,135.47, for a revised lump sum contract amount of $16,808,250.38. District 6. (Capital Projects Division)

body


PROJECT:
Multicultural Center for Design & Innovation and Senior Center Construction

 

PURPOSE: To provide funding for additional construction services to complete the capital improvements.

 

BUDGET: Accounting Line Numbers: 5896-019-0162-6210 and 0001-023-0529-6210

 

JUSTIFICATION/DISCUSSION:

This Change Order provides for the purchase, installation, and integration of additional specialized equipment required for the Orange County Innovation Center that was not included in the original construction contract. The added equipment supports the Center’s intended technology, fabrication, multimedia, virtual reality, and interactive programming capabilities and is necessary to provide a fully functional facility consistent with the County’s operational objectives.

 

PREVIOUS ACTIONS TO THIS CONTRACT:

The Contract award was approved on October 29, 2024.

Original Contract dated December 10, 2024                     
Lump sum amount -
$13,171,004

Change Order No. 1 dated December 29, 2025                     
Lump sum amount -
$118,425.52
Misc. Permit Comments & Fees

Change Order No. 2 dated July 2, 2026                                          
Lump sum amount -
$807,408.60
Floor Preparation and Material Change

Change Order No. 3 dated August 7, 2026                                          
Lump sum amount -
$807,408.60
Phase 1 - Innovation Equipment

Proposed Change Order No. 4                                                                                     
Lump sum amount -
$2,326,135.47
Reminder of Phase 1 & Phase 2 - Innovation Equipment

Proposed Final Contract Amount - $16,808,250.38