Legislation Details

File #: 26-0424    Version: 1 Name:
Type: Procurement Status: Consent Agenda
File created: 3/24/2026 In control: Administrative Services Department
On agenda: 4/21/2026 Final action:
Title: Approval of Change Order No. 3, Purchase Order M119086, Back-up Rental Centrifuge, with Centrifuge-Systems, LLC, in the amount of $157,500, for a revised not-to-exceed total amount of $400,500. ([Utilities Department Water Reclamation Division] Procurement Division)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.


Interoffice Memorandum

DATE: March 24, 2026

TO: Mayor Jerry L. Demings and County Commissioners

FROM: Carrie Mathes, FNIGP, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division

CONTACT: Mark Ikeler, P.E., Manager II, Water Reclamation Division

PHONE: 407-254-9705

SUBJECT: Approval of Change Order No. 3, Purchase Order M119086, Back-up Rental Centrifuge

ACTION REQUESTED:
title
Approval of Change Order No. 3, Purchase Order M119086, Back-up Rental Centrifuge, with Centrifuge-Systems, LLC, in the amount of $157,500, for a revised not-to-exceed total amount of $400,500. ([Utilities Department Water Reclamation Division] Procurement Division)
body

PROCUREMENT:
This change order extends the lease period for a rental back-up centrifuge at the South Water Reclamation Facility for the period of May 1, 2026 through September 30, 2026 to support facility operations while repairs are made to one of the fixed centrifuges used in biosolids removal and disposal. Disruption to facility operations can result in regulatory fines and pose environmental threat to the community.
FUNDING:
Funding is available in account number 4420-038-1351-3610.
APPROVALS:
The Water Reclamation Division concurs with this request.
REMARKS:
On September 22, 2025, the Procurement Division issued Purchase Order M119086 to Centrifuge Systems, LLC in the not-to-exceed amount of $148,500 with a period of service from October 15, 2025 through January 15, 2026.
Repairs to the fixed centrifuge began February 1, 2026 and are expected to be completed by July 31, 2026. The lease extension is necessary to remain compliant with regulatory standards while repairs are completed. The lease months beyond the anticipated completion of repairs are requested to ensure repaired unit is operating at regulatory standards before the rental unit is removed.
Previous change orders are as follows:
Change Order No. 1: Increased not-to-exceed amount by $94,500, for a revised not-to-exceed total of $243,000 ...