Legislation Details

File #: 26-0846    Version: 1 Name:
Type: Procurement Status: Consent Agenda
File created: 7/1/2026 In control: Administrative Services Department
On agenda: 8/4/2026 Final action:
Title: Approval of Amendment No. 10, Task Authorization No. 12, Contract Y17-901E, Additional Construction Administration Services for the project, Addition of Variable Frequency Drives for Water Supply Facilities - Oak Meadows WSF and Hidden Springs RF, with CHA Consulting, Inc., in the amount of $4,987.18, for a revised contract amount of $514,832.13. ([Utilities Department Engineering Division] Procurement Division)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Interoffice Memorandum

DATE: July 1, 2026

TO: Mayor Jerry L. Demings and County Commissioners

FROM: Carrie Mathes, FNIGP, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division

CONTACT: Lindy A. Wolfe, P.E. LEED AP, Manager II, Utilities Engineering Division

PHONE: 407-254-9918

SUBJECT: Approval of Amendment No. 10, Task Authorization No. 12, Contract Y17-901E, Addition of Variable Frequency Drives (VFD) for Water Supply Facilities - Oak Meadows Water Supply Facility (WSF) and Hidden Springs Repump Facility (RF)

ACTION REQUESTED:
title
Approval of Amendment No. 10, Task Authorization No. 12, Contract Y17-901E, Additional Construction Administration Services for the project, Addition of Variable Frequency Drives for Water Supply Facilities - Oak Meadows WSF and Hidden Springs RF, with CHA Consulting, Inc., in the amount of $4,987.18, for a revised contract amount of $514,832.13. ([Utilities Department Engineering Division] Procurement Division)
body

PROCUREMENT:
The contractor has encountered unforeseen field conditions that have delayed completion of the Oak Meadows WSF portion of the project beyond the current contract scope. As a result, this amendment will provide additional engineering services under Task 800 - Construction Administration to support the extended construction duration through project completion.
The additional services are required to address the replacement of a recently installed air conditioning unit at the Oak Meadows WSF that was damaged during construction. The originally approved air conditioning unit is no longer available from the manufacturer and must be replaced with a different brand. Engineering services will include review of shop drawings for the replacement unit, on-site coordination during installation, observation of testing and startup activities, and support through project closeout to achieve final completion. This project is located in Districts 1 and 6.

FUNDING:
Funding is available in account numbers...

Click here for full text