File #: 24-889    Version: 1 Name:
Type: Budget/Funding Status: Passed
File created: 6/12/2024 In control: Administrative Services Department
On agenda: 6/18/2024 Final action: 6/18/2024
Title: Approval of Change Order No. 2, Task Authorization No. 3, Contract Y20-905B, Additional Engineering Services for East Water Reclamation Facility (EWRF) Internal Recycle Pump Replacement, with Black & Veatch, in the total amount of $162,200.70, for a revised total award amount of $550,839.66. ([Utilities Department Engineering Division] Procurement Division)
Attachments: 1. 2024-06-18 Administrative Services Department Consent Item-08

title

Approval of Change Order No. 2, Task Authorization No. 3, Contract Y20-905B, Additional Engineering Services for East Water Reclamation Facility (EWRF) Internal Recycle Pump Replacement, with Black & Veatch, in the total amount of $162,200.70, for a revised total award amount of $550,839.66. ([Utilities Department Engineering Division] Procurement Division)