Interoffice Memorandum
DATE: March 4, 2026
TO: Mayor Jerry L. Demings and County Commissioners
THROUGH: Anne Kulikowski, Director, Administrative Services Department
FROM: Sara Flynn-Kramer, Manager, Capital Projects Division
CONTACT: Sara Flynn-Kramer
PHONE: 407-836-0048
DIVISION: Capital Projects
ACTION REQUESTED:
title
Approval of Change Order No 4, Contract Y24-725 Parks Blanchard Park Parking Improvements, with Uribe Site Development Inc in the amount of $49,539.91, for a revised lump sum contract amount of $1,377,739.03. District 5. (Capital Projects Division)
body
PROJECT: Parks Blanchard Park Parking Improvements
PURPOSE: To provide funding for additional construction services to complete the capital improvements.
BUDGET: Accounting Line Number: 1265-062-2157-6310
JUSTIFICATION/DISCUSSION:
This additional work includes some repaving and landscaping work. During the installation of the new asphalt paving work for an expansion of the parking lot, an area of approximately 8,000 SF of the existing parking lot was milled and paved with 2.5" of asphalt because it had degraded and required restorative work. Also, the existing parking lot islands did not have any trees, so 13 3" Live Oak trees were added to the project in the existing islands to meet the intent of the new tree ordinance even though this work was not a part of the permitted plans.
PREVIOUS ACTIONS TO THIS CONTRACT:
The Contract award was approved on April 9, 2024.
Original Contract dated April 29, 2024 Lump sum amount - $1,250,000.00
Change Order No. 1 dated December 31, 2024 Lump sum amount - $ 14,990.96
Conform plans addressing permit comments
Change Order No. 2 dated June 16, 2025 Lump sum amount - $ 3,472.00
Fire hydrant replacement
Change Order No. 3 dated November 4, 2025 Lump sum amount - $ 59,736.16
Additional permit comments for conform plans
Proposed Change Order No. 4 Lump sum amount - $ 49,539.91
Resurfacing and lan...