Interoffice Memorandum
DATE: July 15, 2024
TO: Mayor Jerry L. Demings and County Commissioners
THROUGH: Anne Kulikowski, Director, Administrative Services Department
FROM: Sara Flynn-Kramer, Manager, Capital Projects Division
CONTACT: Sara Flynn-Kramer
PHONE: 407-836-0048
DIVISION: Capital Projects
ACTION REQUESTED:
title
Approval of Change Order No 3, Contract Y23-739 Fire Rescue Training Facility - INVEST - GRANT, with Mulligan Constructors Inc in the amount of $53,059.59, for a revised lump sum contract amount of $39,967,557.17. District 4. (Capital Projects Division)
body
PROJECT: Fire Rescue Training Facility - INVEST - GRANT
PURPOSE: To provide funding for additional construction services to complete the capital improvements.
BUDGET: Accounting Line Number: 1023-034-0727-6210
JUSTIFICATION/DISCUSSION:
This work was required to provide the underground conduit for the primary electrical service for the project. The utility provider included the wire in their scope of work but excluded the conduit. This scope shifted from the utility provider to the general contractor and is not an additional cost of the project. While the total project cost is not increasing, it is necessary to request approval of this change order because we have reached the change order threshold requiring Board approval with this contractor on this project.
PREVIOUS ACTIONS TO THIS CONTRACT:
Original Contract dated May 5, 2023 Lump sum amount - $38,019,365.00
Change Order No. 1 dated July 31, 2023 Lump sum amount - $ 124,291.04
Additional endangered species mitigation
Change Order No. 2 dated May 29, 2024 Lump sum amount - $ 1,770,841.54
Fire training props and equipment
Proposed Change Order No. 3 Lump sum amount - $ 53,059.59
Include underground electrical conduit for the primary
electrical service not installed by utility provider
Proposed Final Contract Amount $39,967,557.17