Skip to main content
Comptroller Main Webpage

The Clerk of the Board is responsible for keeping accurate minutes and maintaining Board records for each Board of County Commissioner (BCC) and Value Adjustment Board (VAB) meeting. In addition, every 4 years, the Clerk of the Board office provides staff support to the Charter Review Commission (CRC) appointed by the BCC. Please contact our office if you need an accessible version of documents on this page, and one will be provided.

Selection options are described below:

1. To search BCC records by meeting date and/or a specific term between September 23, 1869 and December 14, 2010, view the 'BCC Meetings' page.

2. To view BCC records by meeting date between January 4, 2011 through September 22, 2016, scroll down to locate the BCC meeting date.

3.
To search BCC records by a specific term between October 4, 2016 through Present, select the 'Search Records' tab.      

4.    To view VAB records by meeting date between June 20, 2013 through August 21, 2018, scroll down to locate the VAB meeting date. 

5.    To search CRC regular business meeting records by a specific term between February 25, 2019 through Present, select the 'Search Records' tab.

File #: 26-0117    Version: 1 Name:
Type: Procurement Status: Consent Agenda
File created: 12/30/2025 In control: Administrative Services Department
On agenda: 1/27/2026 Final action:
Title: Approval of Amendment No. 7, Contract Y24-809, Construction Manager at Risk (CMAR) Services for the Orange County Convention Center Phase 5A Improvements-Grand Concourse, with Turner Construction Company, Inc., in the amount of $97,117,694 for a revised total contract amount of $129,373,700.31. ([Orange County Convention Center Capital Planning Division] Procurement Division)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Interoffice Memorandum

DATE: December 31, 2025

TO: Mayor Jerry L. Demings and County Commissioners

FROM: Carrie Mathes, FNIGP, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division

CONTACT: Terry Devitt, Deputy Director, Orange County Convention Center

PHONE: 407-685-9867

SUBJECT: Approval of Amendment No. 7, Contract Y24-809, Construction Manager at Risk (CMAR) Services for the Orange County Convention Center Phase 5A Improvements-Grand Concourse

ACTION REQUESTED:
title
Approval of Amendment No. 7, Contract Y24-809, Construction Manager at Risk (CMAR) Services for the Orange County Convention Center Phase 5A Improvements-Grand Concourse, with Turner Construction Company, Inc., in the amount of $97,117,694 for a revised total contract amount of $129,373,700.31. ([Orange County Convention Center Capital Planning Division] Procurement Division)
body

PROCUREMENT:
This amendment adds the second portion of the Guaranteed Maximum Price ("GMP #2") which includes a strategically targeted long-lead procurement package that positions the project to remain on schedule and budget by securing pricing for critical early components to align fabrication and delivery timelines with the start of major construction activities in early 2026.
Key Components of GMP #2 include:
? Structural Steel & Miscellaneous Metals: Covering the procurement of all structural steel necessary for a steel mill order.
?Deep Foundations & Test Pile Program: Early release of deep foundation work-including test piles-is incorporated to ensure geotechnical verification and sequencing continuity.
?Other Long-Lead Items: Includes early procurement for electrical gear and mechanical equipment requiring advance release before the main construction GMP.
The price for this phase is considered fair and reasonable based on the CMAR competitively bidding packages to multiple qualified contractors, including several steel, concrete pile, mechanical, and electrical contractors, as well as national ...