Interoffice Memorandum
DATE: June 11, 2026
TO: Mayor Jerry L. Demings and County Commissioners
THROUGH: N/A
FROM: Joseph C. Kunkel, P.E., Director, Public Works Department
CONTACT: Eduardo Avellaneda, P.E., Manager
PHONE: (407) 836-7871
DIVISION: Roads and Drainage Division
ACTION REQUESTED:
title
Approval of Change Order No. 4, Contract 25703-2 L.B.McLeod Road Bridge over Shingle Creek Steel Beam Rehab and Recoating Project Phase 2 and 3 with Southern Road and Bridge LLC in the amount of $380,196.75, for a revised total contract amount of $1,651,978.75. District 6. (Roads and Drainage Division)
body
PROJECT: N/A
PURPOSE:
Change Order No. 4 to Contract No. 25703-2 is required for the L.B. McLeod Road Bridge over Shingle Creek Steel Beam Rehabilitation and Recoating Project - Phase 2 and 3 Project. This change order, in the amount of $380,196.75, increases the contract amount from $1,271,782.00 to $1,651,978.75, an increase of 29.89%. It also includes a time extension from June 30, 2026 through September 30, 2026 to complete work and submittals.
The current change order is required for additional work and materials to install pile jackets on concrete piles that exhibit surface deterioration and to replace the existing guardrail with one that meets current safety standards.
A summary of previous change orders is listed below:
Change Order No. 1 - increased the original contract amount from $1,165,792 to $1,236,882.
Change Order No. 2 - time extension from December 21, 2025 through March 31, 2026.
Change Order No. 3 - increased the contract amount from $1,236,882 to $1,271,782.
Funds for this change order will be available in accounting line 1004-072-2912-3816.