Skip to main content
Comptroller Main Webpage

The Clerk of the Board is responsible for keeping accurate minutes and maintaining Board records for each Board of County Commissioner (BCC) and Value Adjustment Board (VAB) meeting. In addition, every 4 years, the Clerk of the Board office provides staff support to the Charter Review Commission (CRC) appointed by the BCC. Please contact our office if you need an accessible version of documents on this page, and one will be provided.

Selection options are described below:

1. To search BCC records by meeting date and/or a specific term between September 23, 1869 and December 14, 2010, view the 'BCC Meetings' page.

2. To view BCC records by meeting date between January 4, 2011 through September 22, 2016, scroll down to locate the BCC meeting date.

3.
To search BCC records by a specific term between October 4, 2016 through Present, select the 'Search Records' tab.      

4.    To view VAB records by meeting date between June 20, 2013 through August 21, 2018, scroll down to locate the VAB meeting date. 

5.    To search CRC regular business meeting records by a specific term between February 25, 2019 through Present, select the 'Search Records' tab.

File #: 26-0245    Version: 1 Name:
Type: Procurement Status: Consent Agenda
File created: 2/5/2026 In control: Administrative Services Department
On agenda: 3/10/2026 Final action:
Title: Approval to award Invitation for Bids Y25-783-CC, All American Boulevard Construction from Clarcona-Ocoee Road to Forest City Road (CIP 3097)/Kennedy Boulevard Widening Project from All American Boulevard to Kingston Court (CIP 3096), to the low responsive and responsible bidder, Granite Construction Company, in the total contract award amount of $40,956,902.16. In the event the bidder recommended above fails to achieve timely compliance with pre-award deliverables, as defined in the Invitation for Bids, including, but not limited to, State Division of Corporations registration, E-verify, insurance and bonds, further request Board authorization for the Procurement Division to award to the next low responsive and responsible bidder as listed in the bid tabulation herein, to the extent practicable and advantageous to the County. ([Public Works Department Engineering Division] Procurement Division)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Interoffice Memorandum

DATE: February 5, 2026

TO: Mayor Jerry L. Demings and County Commissioners

FROM: Carrie Mathes, FNIGP, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division

CONTACT: Raymond Williams, Manager, Public Works Engineering Division

PHONE: 407-836-7909

SUBJECT: Award of Invitation for Bids Y25-783-CC, All American Boulevard Construction from Clarcona-Ocoee Road to Forest City Road (CIP 3097)/Kennedy Boulevard Widening Project from All American Boulevard to Kingston Court (CIP 3096)

ACTION REQUESTED:
title
Approval to award Invitation for Bids Y25-783-CC, All American Boulevard Construction from Clarcona-Ocoee Road to Forest City Road (CIP 3097)/Kennedy Boulevard Widening Project from All American Boulevard to Kingston Court (CIP 3096), to the low responsive and responsible bidder, Granite Construction Company, in the total contract award amount of $40,956,902.16.

In the event the bidder recommended above fails to achieve timely compliance with pre-award deliverables, as defined in the Invitation for Bids, including, but not limited to, State Division of Corporations registration, E-verify, insurance and bonds, further request Board authorization for the Procurement Division to award to the next low responsive and responsible bidder as listed in the bid tabulation herein, to the extent practicable and advantageous to the County. ([Public Works Department Engineering Division] Procurement Division)

body

PROCUREMENT:
All American Boulevard - Clarcona-Ocoee Road to Forest City Road (CIP No. 3097):
This project realigns All American Boulevard to connect with Edgewater Drive and Clarcona-Ocoee Road. Work includes 0.67 miles of new four-lane divided roadway, 0.14 miles of improvements on existing All American Boulevard, and 0.28 miles of improvements on Edgewater Drive. Additional features include sidewalks, driveways, curb ramps, medians, railroad crossing upgrades, stormwater ponds, a box culvert at the Little Wekiva Canal, landsc...