Legislation Details

File #: 24-1321    Version: 1 Name:
Type: Recommendation Status: Passed
File created: 8/21/2024 In control: Public Works Department
On agenda: 9/10/2024 Final action: 9/10/2024
Title: Approval and execution of (1) Resolution 2024-M-32 of the Orange County Board of County Commissioners regarding the Local Agency Program Agreement with the State of Florida Department of Transportation concerning the University Boulevard at Dean Road Intersection Project (FPN Number 441490-1-58/68-01) and (2) State of Florida Department of Transportation Local Agency Program Agreement FPN: 441490-1-58-01 and FPN: 441490-1-68-01. District 5. (Transportation Planning Division)
Attachments: 1. 24-1321_ Resolution University Boulevard at Dean Road LAP 439252-1-58-68-01, 2. 24-1321_4414910-1-58.68-01 (FY25) - LAP - Univ. Blvd, 3. 2024-09-10 Public Works Department Consent Item-06, 4. Resolution 2024-M-32

Interoffice Memorandum

 

DATE: August 21, 2024

 

TO: Mayor Jerry L. Demings and County Commissioners

 

THROUGH: N/A

 

FROM: Joseph C. Kunkel, P.E., Director, Public Works Department

 

CONTACT: Brian R. Sanders, Manager

 

PHONE: (407) 836-8022

 

DIVISION: Transportation Planning Division

 

ACTION REQUESTED:

title

Approval and execution of (1) Resolution 2024-M-32 of the Orange County Board of County Commissioners regarding the Local Agency Program Agreement with the State of Florida Department of Transportation concerning the University Boulevard at Dean Road Intersection Project (FPN Number 441490-1-58/68-01) and (2) State of Florida Department of Transportation Local Agency Program Agreement FPN: 441490-1-58-01 and FPN: 441490-1-68-01.  District 5. (Transportation Planning Division)

body


PROJECT:
N/A

 

PURPOSE:
The Public Works Department has completed the design for intersection improvements at University Boulevard and Dean Road.  The Transportation Planning Division requested federal funding through MetroPlan Orlando and the Florida Department of Transportation (FDOT) for construction and construction engineering inspection (CEI) in the amount of $7,833,509; however, $6,054,954 is available in federal funds.  Orange County will fund the remaining construction and CEI in the amount of $1,778,555. 

The intersection project includes traffic signalization and pavement markings, signage, milling and resurfacing, pavement widening, sidewalks, a concrete traffic separator, curb and gutter, and drainage improvements. 

FDOT has requested approval of a resolution and Local Agency Program Agreement.  The County Attorney’s Office, Risk Management Division, Public Works Engineering Division, and Transportation Planning Division have reviewed this Resolution and Agreement and find them acceptable.

 

BUDGET: N/A