Title: Approval of Change Order No 5, Contract Y22-733 Multicultural Center INVEST - GRANT, with Oelrich Construction Inc in the amount of $54,725.85, for a revised lump sum contract amount of $4,922,923.52. District 6. (Capital Projects Division)
Attachments: 1. 2023-09-12 Administrative Services Department Consent Item 3

title

Approval of Change Order No 5, Contract Y22-733 Multicultural Center INVEST - GRANT, with Oelrich Construction Inc in the amount of $54,725.85, for a revised lump sum contract amount of $4,922,923.52. District 6. (Capital Projects Division)