Title: Approval of Amendment No.1, Contract Y20-826, Professional Construction Engineering & Inspection (CEI) Services & Resident Compliance Specialist Services for Shingle Creek Trail Phase 1 Segment 2 (from S.R. 528 to Destination Parkway) Construction Project, with CDM Smith Inc., in the amount of $157,253.52, for a revised total contract award amount of $866,041.38 ([Public Works Department Highway Construction Division] Procurement Division)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Interoffice Memorandum

DATE: July 30, 2026

TO: Mayor Jerry L. Demings and County Commissioners

FROM: Carrie Mathes, FNIGP, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division

CONTACT: Ken Leeming, P.E., Manager, Highway Construction Division

PHONE: 407-836-7713

SUBJECT: Approval for Amendment No. 1, Contract Y20-826, Professional Construction Engineering and Inspection (CEI) and Resident Compliance Specialist Services for Shingle Creek Phase 1 Segment 2 (from S.R. 528 to Destination Parkway) Construction Project

ACTION REQUESTED:
title
Approval of Amendment No.1, Contract Y20-826, Professional Construction Engineering & Inspection (CEI) Services & Resident Compliance Specialist Services for Shingle Creek Trail Phase 1 Segment 2 (from S.R. 528 to Destination Parkway) Construction Project, with CDM Smith Inc., in the amount of $157,253.52, for a revised total contract award amount of $866,041.38 ([Public Works Department Highway Construction Division] Procurement Division)
body

PROCUREMENT:
The subject LAP-funded CEI contract Y20-826 (430225-5-68-01) was executed before construction of the corresponding construction project was placed on hold in 2021. The construction project has since been re-bid under Invitation for Bids Y24-722. The resulting construction contract was approved for award by the Board and executed on July 20, 2026.
To align the CEI contract with the revised construction schedule, an amendment has been prepared to extend the duration of Contract Y20-826 by 345 days. The amendment will also update the original 2020 unit rates to the negotiated 2026 rates approved by Florida Department of Transportation and their pre-approved multipliers. The proposed amendment does not modify the scope of work and is limited to revising the contract duration and applicable unit rates. This amendment will be fully funded by the LAP Agreement via a Supplemental Agreement.


FUNDING:
Funding is contingent upon the supplemental LAP agreement that is...