Interoffice Memorandum
DATE: February 20, 2025
TO: Mayor Jerry L. Demings and County Commissioners
FROM: Carrie Mathes, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division
CONTACT: Raymond Williams, Manager, Public Works Engineering Division
PHONE: 407-836-7909
SUBJECT: Selection of Consultant, Request for Proposals Y25-802-MB, Final Engineering Design Services for the West Orange Trail - Phase 4B
RECOMMENDATION:
title
Selection of one firm and an alternate to provide Final Engineering Design Services for the West Orange Trail - Phase 4B, Request for Proposals Y25-802-MB from the firms listed alphabetically:
* Avcon, Inc.
* WBQ Design & Engineering, Inc.
Request Board authorization for the Procurement Division to negotiate and execute a contract with a not to exceed budget amount of $2,130,912. Further request Board authorization for the Procurement Division to formally terminate negotiations with the top ranked firm, if we are unable to come to a favorable negotiated agreement, and commence negotiations with the next ranked alternate, until a successful negotiation is reached. ([Public Works Department Engineering Division] Procurement Division)
body
PROCUREMENT:
The Consultant shall provide final engineering design and construction plan preparation and shall perform those engineering services required to prepare a complete set of contract documents (plans and specifications) as described in the Request for Proposals (RFP).
The Consultant shall use the design concepts provided in the West Orange Trail Extension Study prepared by MetroPlan Orlando and meet the requirements of the State-Funded Grant Agreement as approved by the Board of County Commissioners and the Florida Department of Transportation. The Consultant shall perform the required engineering services utilizing all the applicable materials and data collected and provided in the study. This project is located in District 2.
FUNDING:
Funding is available in account number 8750...
Click here for full text