Interoffice Memorandum
DATE: April 30, 2026
TO: Mayor Jerry L. Demings and County Commissioners
FROM: Carrie Mathes, FNIGP, CFCM, NIGP-CPP, CPPO, C.P.M., Manager II, Procurement Division
CONTACT: Humberto Castillero, Manager, Traffic Engineering Division
PHONE: 407-836-7891
SUBJECT: Approval of Change Order No. 3, Task Authorization No. 11, Contract Y22-905, Continuing Professional Consulting Services, Engineering and Inspection (CEI) Services
ACTION REQUESTED:
title
Approval of Change Order No. 3, Task Authorization No. 11, Contract Y22-905, Continuing Professional Consulting Services, Engineering and Inspection (CEI) Services, with CDM Smith, Inc., in the amount of $136,491.12, for a revised total amount of $499,846.32. ([Public Works Department Traffic Engineering Division] Procurement Division)
body
PROCUREMENT:
This change order provides funding for an additional 1,040 man-hours required for staff augmentation services within the Traffic Engineering Division. The additional hours are necessary to support Construction Engineering and Inspection (CEI) services for the Y26-720-EB Seidel Road at Summerlake Park Boulevard Roundabout Improvement project throughout the full construction duration and project closeout phase. The construction timeline for Contract Y26-720 is estimated to take approximately 10 to 12 months, requiring CEI services to be provided throughout the entire construction process to ensure compliance with project specifications, safety standards, and contract requirements.
The additional CEI support will provide adequate staffing to perform daily construction inspections, coordinate with the contractor and project stakeholders, monitor project progress, maintain required project documentation, address field issues, and complete final project closeout activities.
FUNDING:
Funding is available in account number 1002-072-2711-3179.
APPROVALS:
The Traffic Engineering Division concurs with this recommendation.
REMARKS:
On August 9, 2022, th...