Title: Approval and execution of (1) Resolution 2024-M-45 of the Orange County Board of County Commissioners regarding the Local Agency Program Supplemental Agreement with the State of Florida Department of Transportation concerning the Lake Apopka Trail Connector (FPN Number 441447-1-58/68-01) and (2) State of Florida Department of Transportation Local Agency Program Supplemental Agreement FPN: 441447-1-58/68-01 Contract No.: G2R75. District 2. (Transportation Planning Division)
Attachments: 1. 24-1579_ SA #1 - Lake Apopka Trail Connector Project, 2. 24-1579_LAP Supplemental Resolution Lake Apopka Trail Connector 441447-1-58 68-01, 3. 2024-10-29 Public Works Department Consent Item-06, 4. Resolution 2024-M-45
Interoffice Memorandum

DATE: October 14, 2024

TO: Mayor Jerry L. Demings and County Commissioners

THROUGH: NA

FROM: Joseph C. Kunkel, P.E., Director, Public Works Department

CONTACT: Brian R. Sanders, Manager

PHONE: (407) 836-8022

DIVISION: Transportation Planning Division

ACTION REQUESTED:
title
Approval and execution of (1) Resolution 2024-M-45 of the Orange County Board of County Commissioners regarding the Local Agency Program Supplemental Agreement with the State of Florida Department of Transportation concerning the Lake Apopka Trail Connector (FPN Number 441447-1-58/68-01) and (2) State of Florida Department of Transportation Local Agency Program Supplemental Agreement FPN: 441447-1-58/68-01 Contract No.: G2R75. District 2. (Transportation Planning Division)
body

PROJECT: NA

PURPOSE:
The Public Works Department has solicited construction services for the Lake Apopka Trail Connector project. This project will extend the existing Lake Apopka Loop Trail near Magnolia Park and connect to the West Orange Trail. Portions of this trail are being constructed by through the Oak Point North and Wynwood developments. The proposed trail will include a 10' to 14' wide asphalt and concrete trail, gravity walls, curb and gutter, detectable warning surfaces, fencing, landscaping, signing and pavement markings, flashing signs, rectangular rapid flashing beacons, bicycle racks, trash receptacles, benches, rest area shelters, water fountains, drainage improvements and grading. The project length is approximately 3,219 feet.

This project is funded in accordance with the Local Agency Program (LAP) Agreement that was approved by the Board on February 21, 2023. Due to inflationary effects realized during the approval of the construction bid, the project cost has increased from $5,875,906 to $8,588,048. The Florida Department of Transportation and MetroPlan Orlando have agreed to increase the federal fund amount to $5,282,758 (formally $4,000,000) and the County's...

Click here for full text