Title: Approval and execution of (1) License Agreement by and between Florida Central Railroad Company, LLC and Orange County, Florida ORAN-60-354, (2) License Agreement by and between Florida Central Railroad Company, LLC and Orange County ORAN-14-355, and (3) License Agreement between Florida Central Railroad Company, LLC and Orange County Florida ORAN-64-356, in the total amount of $94,500, all for the construction and maintenance of a drainage conveyance system in addition to a conduit and a pedestrian signal within the railroad right of way on the extension of All American Boulevard. District 2. (Engineering Division)
Attachments: 1. 9.29.2026_26-1158_FCEN ORAN-60-354, 2. 9.29.2026_26-1158_FCEN ORAN-14-355, 3. 9.29.2026_26-1158_FCEN ORAN-64-356
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Interoffice Memorandum

DATE: September 9, 2026

TO: Mayor Jerry L. Demings and County Commissioners

THROUGH: N/A

FROM: Joseph C. Kunkel, P. E., Director, Public Works Department

CONTACT: Raymond L.A. Williams, P.E., Manager

PHONE: (407) 836-7909

DIVISION: Engineering Division

ACTION REQUESTED:
title
Approval and execution of (1) License Agreement by and between Florida Central Railroad Company, LLC and Orange County, Florida ORAN-60-354, (2) License Agreement by and between Florida Central Railroad Company, LLC and Orange County ORAN-14-355, and (3) License Agreement between Florida Central Railroad Company, LLC and Orange County Florida ORAN-64-356, in the total amount of $94,500, all for the construction and maintenance of a drainage conveyance system in addition to a conduit and a pedestrian signal within the railroad right of way on the extension of All American Boulevard. District 2. (Engineering Division)
body

PROJECT: N/A

PURPOSE:
The Public Works Department is currently constructing All American Boulevard, a new four-lane urban section roadway from the intersection of Edgewater Drive and Clarcona Ocoee Road to just west of Forest City Road. This project is being constructed together with improvements to the contiguous western segment of Kennedy Boulevard that extends from just west of Forest City Road to Kingston Court. The projects have a combined length and construction cost of 1.9 miles and approximately $41.6M, respectively.

Three agreements with Florida Central Railroad Company, LLC (FCEN) were previously approved by the Board in December 2025. Those agreements facilitate the current construction, use and maintenance of a new railroad crossing, and an existing railroad crossing as part of the All American Boulevard Project.

The above captioned license agreements were negotiated with FCEN for the construction and maintenance of drainage conveyance systems together with an underground conduit and a pedestrian signal within the rail...